RL.2.6 Delivery Performance to Original Supplier Commit Date

METRIC RL Level 2

Definition

The percentage of orders that are fulfilled on or before the internal Commit date, used as a measure of internal scheduling systems' effectiveness. Delivery measurements are based on the date a complete order is shipped or the ship-to date of a complete order. A complete order has all items on the order delivered in the quantities requested. An order must be complete to be considered fulfilled. Multiple line items on a single order with different planned delivery dates constitute multiple orders, and multiple planned delivery dates on a single line item also constitute multiple orders.

Formula / Calculation

Delivery Performance to Original Supplier Commit Date = [Total number of orders delivered in full and on time to the scheduled commit date] / [Total number of orders delivered]